Royal Coast Construction L.L.C — Abu Dhabi, UAE
Royal Coast Construction L.L.C is specialized in plans, executes and controls Demolition, Excavation and Back-filling solutions in all over the UAE.

Project Scope

Works cover selective/total demolition of existing structures, removal of obstructions, excavation to required levels, temporary shoring where required, disposal of demolition spoil, and supply/placement/compaction of back-fill and imported materials to engineered levels. Works include all temporary works, reinstatement, testing, QA/QC, safety, environmental controls and required permits.

Pre-Mobilization & Planning

Site survey & records review

Review existing drawings, utilities maps, structural drawings, previous site investigations, and as-built documents. Carry out measured surveys and photographic records.

Dilapidation & condition surveys

Record adjacent buildings, roads, utilities and finishes before works begin.

Utility detection & potholing

Record adjacent buildings, roads, utilities and finishes before works begin.

Hazardous materials survey

Inspect for asbestos, lead paint, contaminated soil or hydrocarbons; arrange licensed removal if present.

Permits & approvals

Secure demolition permit, NOC for traffic management, waste transfer (hazardous if any), and Abu Dhabi Municipality/ERD approvals where required.

Method statement & RAMS

Produce detailed method statement, Risk Assessment and Method Statement (RAMS), emergency plan, and environmental management plan (EMP).

Stakeholder Coordination

Notify neighbors, arrange traffic/road closures, and coordinate with client and authorities for working hours and noise controls.

Demolition Works

Types of Demolition

Sequence & Controls

Waste Handling & Recycling

Excavation Works

Pre-Excavation

Excavation Methods

Monitoring

Back-Filling & Compaction

Material Selection

Reusable Material

Approved crushed concrete (after testing), selected excavated granular material.

Imported Fill

Natural sand, crushed rock, engineered fill or specified granular sub-base (as per project spec). Provide material certificates, gradation, and contamination tests.

Method statement & RAMS

Produce detailed method statement, Risk Assessment and Method Statement (RAMS), emergency plan, and environmental management plan (EMP).

Placement & Compaction

Place back-fill in controlled lifts (typical 150–300 mm loose thickness depending on equipment and material). Compact each lift to specified relative compaction (e.g., ≥95% Modified Proctor or as engineered). Use plate compactors, rammers, or vibratory rollers per lift thickness and material. Pay special care when back-filling around buried services: use free-flowing bedding sand and hand-compaction adjacent to pipes. Provide geotextile or geogrid where specified for separation/stabilization.

Testing

In-situ density tests (nuclear gauge or sand replacement) at defined frequencies. Moisture content control and adjustment. Laboratory gradation and Proctor tests on representative samples. CBR testing for pavement subgrade where required.

Temporary Works & Reinstatement

Health, Safety & Environment (HSE)

Quality Assurance & Documentation

Documents issued and maintained

method statement, RAMS, permits, survey records, daily activity logs, photographic records, material delivery notes, waste manifests and test reports.

Inspection & testing regime

pre-excavation survey, compaction/density tests, material lab tests and final as-built survey.

Acceptance criteria

all fills to meet specified density, moisture content and gradation; excavations within line/level tolerances; demolition complete with required clearance certificates.

Handover pack

includes test certificates, inspection logs, waste disposal records, as-built drawings and compliance certificates.

Equipment & Typical Resources

Risk Highlights & Mitigation

UAE Considerations

Deliverables to Client